YEP worked for two weeks on Phase 1 of a two year project that will connect the Chugach
Foothills community to the trail system and Far North Bicentennial. The crews helped build 0.7
miles of trail through 1,200 feet of wetland including two stream crossings.
The project consisted of:
• Grubbing existing vegetation along 0.7 miles of an existing social trail
• Laying geo-synthetic woven textile
• Hauling 515 tons of gravel
• Building a 12 ft. sustainable fiberglass decking, timber framed footbridge
Project Dates:
June 13 – 25
MOA Funds: $32,000
Private Funding: $41,000